2 Cell Cooling Tower – Orica Yarwun

Orica Yarwun

Replacement two (2) Cell tower for the existing BAC double side cross flow.

New tower was pre-constructed in sections for a change over during an 18 day outage in March 2017

This project had another tight change over time frame that Breezewater successfully met within 18 days.

The tower delivered an additional 15% capacity without increasing operational costs.

This project had another tight change over time frame that Breezewater successfully met within 18 days.

The tower delivered an additional 15% capacity without increasing operational costs.

The challenge of removing the existing BAC tower without damaging the concrete basin meant that the traditional demolition process was not appropriate. Breezewater engineering and construction team conducted a detailed review and developed a dismantling procedure to lift out the tower in sections with no damage to the concrete basin.

Scroll to Top